Road Construction Report: May 8, 2014

Tools

By WSIL Manager

WSIL -- Below is the Illinois Department of Transportation District 9 road construction report for Thursday, May 8, 2014.
 
 
FRANKLIN COUNTY 
 
Interstate 57, 4 Bridges at MP 60, 63, 71 and 77
Bridge painting
Minor delays expected
Estimated completion date: 12/1/2014
 
Illinois 37, Yellow Banks Road to Douglas, West Frankfort
Patch and resurface
Minor delays expected
Estimated completion date: 7/1/2014
 
Illinois 149, 16 miles east of West Frankfort
Box culvert replacement
Minor delays expected
Estimated completion date: 7/19/2014
 
Illinois 37 intersection with Illinois 149 in West Frankfort
Traffic signals
Minor delays expected
Estimated completion date: 6/30/2014
 
 
HAMILTON COUNTY
 
Illinois 142, 1 Mile South of Broughton
Replace culvert
Minor delays expected
Estimated completion date: 5/30/2014
 
 
JACKSON COUNTY
 
Illinois 13 in Murphysboro at the Big Muddy River bridges
Bridge replacement
Minor delays expected
Estimated completion date: 12/1/2014
 
 
MASSAC COUNTY
 
Interstate 24, 3.5 miles east of Metropolis over the Ohio River
Bridge joint repair
Minor delays expected
Estimated completion date: 7/19/2014
 
 
PERRY COUNTY
 
Illinois 154, Pinckneyville Square to Perry/Randolph county line
Patch, resurface and bridge work
Minor delays expected
Estimated completion date: 5/30/2014
 
 
POPE COUNTY
 
Illinois 146, east of Illinois 145
Bridge replacement
Minor delays expected
Estimated completion date: 9/17/2014
 
 
WHITE COUNTY
 
Illinois 1 over McHenry Slough, 2 miles northeast of Carmi
Bridge replacement
Minor delays expected
Estimated completion date: 6/1/2014
 
Interstate 64, 6.5 miles east of Wayne County line to Illinois 1
Patch, mill and resurface
Minor delays expected
Estimated completion date: 12/1/2015
 
Illinois 1 / 14, 2 miles south of Crossville
Bridge replacement
Minor delays expected
Estimated completion date: 12/1/2015
 
Illinois 1, 3 Miles south of Carmi
Bridge replacement
Minor delays expected
Estimated completion date: 9/9/2014
 
Illinois 14, Hamilton County line to Carmi 
Resurfacing
Minor delays expected
Estimated completion date: 6/13/2014
 
 
WILLIAMSON COUNTY
 
Illinois 13 at the railroad tracks west of Marion
Grade raise and add lanes
Minor delays expected
Estimated completion date: 6/1/2014
 
Interstate 57, 4 bridges at MP 60, 63, 71 and 77
Bridge painting
Minor delays expected
Estimated completion date: 12/1/2014
 
Illinois 13, Russell Street to Illinois 37
Additional lanes
Minor delays expected
Estimated completion date: 8/15/2014
 
I-57 & Illinois 13 in Marion at interchange
Interchange replacement
Minor delays expected
Estimated completion date: 12/1/2014
 
I-57, Morgan Ave in Marion to 4 miles north
Additional lanes
Major delays expected
Estimated completion date: 11/30/2014
 
Illinois 13, Commercial Drive to Crainville Road in Carterville
Additional lanes
Minor delays expected
Estimated completion date: 10/15/2015
 
Illinois 13 Frontage Rd, Frontage Road north of Illinois 13 in Carterville from Division to Wolf Creek
Construct new frontage road
Minor delays expected
Estimated completion date: 5/30/2014
 
Illinois 37, 0.5 miles north of Johnson County line at Pulley's Mill
Super-elevation correction
Minor delays expected
Estimated completion date: 7/24/2014

 

 

 